Italian News Headlines 09-10-2025: Claudia Cardinale, legend of Italian cinema, has died at the age of 87 | The Italian women's volleyball team has won the World Championships, their 36th consecutive victory | Legendary Italian fashion designer, Giorgio Armani, has died at the age of 91 | Italian authorities are expecting over 12 million vehicles on the roads over the 'Ferragosto' weekend | 45 people were injured in Rome when a petrol station exploded, following a smaller explosion caused by a truck hitting a gas pipe | Twenty Italian seaside resorts have been awarded Cinque Vele status by the Legambiente and Touring Club Italiano, of which six are in Sardinia. The beach at Domus de Maria, in southern Sardinia, has received the highest ranking in 2025 | The world's most famous Tik Toker, Italian, Kharby Lame, was arrested and then expelled from the United States for remaining in the country after his visa expired | The Italian navy training ship, Amerigo Vespucci, arrived in Cagliari to be welcomed by Luna Rossa, the winner of the 37th America's Cup youth and women's tournament | Italy will host the 38th edition of the America's Cup in Naples in 2027 | Robert Francis Prevost from the USA has been chosen as the new pope, taking the name, Pope Leo XIV

Genoa Bridge Rebuild

Genoa Bridge Rebuild
Rosa Mauro, CC BY-SA 4.0, via Wikimedia Commons

On August 14, 2018, a 210-meter section of the Morandi Bridge in Genoa collapsed during a torrential storm, causing 43 tragic fatalities and displacing over 600 residents.

The disaster sparked international attention and became a symbol of failing infrastructure, urging both Italy and the European Union to reassess how aging transport networks are monitored and maintained.

Understanding the original Morandi Bridge design

The original bridge, opened in 1967, was a cable-stayed structure designed by renowned Italian engineer Riccardo Morandi and hailed as an architectural marvel of its time.

Built using prestressed concrete, the bridge featured a unique system of stays enclosed in sheaths, which later proved difficult to inspect and maintain over decades of environmental exposure.

Factors contributing to the structural failure

The causes of the collapse were complex and included corrosion of internal cables, insufficient maintenance, and design limitations that were not fully understood at the time of construction.

Investigations revealed that load demands had far exceeded what the bridge was originally designed to handle, especially with growing urban traffic and logistics transport through Liguria.

The urgent need for a new Liguria infrastructure model

The Genoa disaster highlighted not only the specific failure of a single bridge but also the broader challenges facing Liguria and Italian infrastructure in general.

The Italian government responded with rapid action, pushing through emergency legislation to expedite the demolition of the remains and commission a new bridge in record time.

Commissioning and planning the new Genoa bridge

Architect Renzo Piano, a Genoa native, was selected to lead the design of the new bridge, bringing a vision of light, resilience, and continuity to the devastated area.

The construction contract was awarded to a joint venture between Fincantieri Infrastructure and Salini Impregilo, later renamed Webuild, two of Italy’s top engineering firms.

Design features of the new Genova San Giorgio bridge

The new bridge, named Genova San Giorgio, spans 1,067 meters and consists of 19 elliptical steel spans supported by 18 reinforced concrete piers spaced every 50 meters.

The design reflects maritime inspiration with its sleek, ship-like profile and was engineered for a lifespan of 100 years, with minimal maintenance and advanced monitoring systems.

Smart monitoring and digital integration

One of the key innovations in the new bridge is the integration of digital monitoring systems, using sensors that continuously measure strain, vibration, temperature, and seismic activity.

This data is transmitted in real time to maintenance teams and government agencies, forming part of Italy’s shift towards predictive infrastructure maintenance strategies.

Sustainability and energy efficiency of the new structure

The Genova San Giorgio bridge incorporates photovoltaic panels that power its lighting system, contributing to its energy efficiency and reducing its environmental impact.

Its piers are coated in anti-corrosion materials while air filtration systems were installed to protect the nearby neighborhoods from dust and micro-particles during and after construction.

Construction timeline and speed of execution

The demolition of the Morandi Bridge began in February 2019 and was completed in just a few months, clearing the site for construction to begin in April 2019.

Remarkably, despite the COVID-19 pandemic, the new bridge was completed in just over a year and inaugurated on August 3, 2020, setting a record for infrastructure rebuilding speed.

Engineering under emergency legislation

To meet the urgent need, Italy invoked emergency powers, appointing a special commissioner with authority to bypass standard procurement and environmental approval processes.

This controversial but effective measure allowed design, approval, and construction phases to overlap, drastically reducing the total project duration compared to traditional models.

Public-private collaboration and financing

The reconstruction project was primarily funded by the Italian government with supplementary investment from Autostrade per l’Italia, the former bridge operator, under intense public scrutiny.

The collaboration between public institutions and private firms provided a model of fast-track infrastructure development, combining accountability with high-quality engineering.

The bridge as a symbol of hope and engineering success

For Liguria and beyond, the Genova San Giorgio bridge stands as a testament to resilience, unity, and the possibilities of engineering when driven by urgency and purpose.

Its elegant profile has become a symbol of healing for the community, showing how infrastructure can be designed not only for function but also for memory and identity.

Lessons for global infrastructure resilience

Countries worldwide have taken note of the Genoa case as a pivotal moment in understanding the importance of proactive infrastructure maintenance and digital monitoring.

The combination of smart design, sustainability, speed, and oversight sets a new benchmark for how future bridge projects can evolve under pressure and technological advancement.

What comes next for Liguria’s infrastructure landscape

Following the successful completion of the bridge, Liguria is now undertaking a comprehensive audit of its entire road and rail system, with major updates planned for tunnels and viaducts.

Public awareness and political will have aligned, creating momentum for a long-overdue investment wave that could transform the region into a model of modern European connectivity.

Conclusion: a model of modern infrastructure engineering

The Genoa bridge project is more than a replacement of a fallen structure, it is a global case study in engineering resilience, disaster response, and smart construction planning.

Its rapid execution, elegant design, and integrated technology have positioned it as one of the most significant infrastructure achievements in recent European history.

The Best Italian Handmade Gifts
Direct From Italy

Orione Necklace - Murano beads with cosmic pattern

More Details

sail to italy
Other pages you might like
Newsletter
Enter your email address below to receive our free newsletter, 'I Love Italy'. It provides a captivating glimpse into the allure of 'The Bel Paese', containing extracts from our most recent articles, a window on Italian news, fashion, music and culture, useful information for visiting and living in Italy as well as our latest, delicious Italian recipes.

Subscribers are also entitled to a 10% discount on purchases from our sister-site, Italy Gifts Direct.

We will not use your email address for any other purpose or pass it on to any other organisation and you can unsubscribe from this service at any time.
I agree to receive occasional emails and have read the Privacy Policy.

up arrow